Another Fire Hits Joburg Central Substation, Plunging CBD Areas Back Into Darkness

 Residents and businesses in Johannesburg’s inner city are facing another electricity disruption after a fourth fire at City Power’s Central Substation triggered a fresh outage on Tuesday, October 13, 2026.

The latest incident damaged feeder board 4 at the substation in Marshalltown, adding to a series of fires and technical problems that have repeatedly interrupted electricity supplies across parts of the central business district.

City Power teams and emergency personnel were at the site, but smoke and flames prevented technicians from safely accessing the underground cable tunnel to assess the full extent of the damage.

Which Areas Are Affected?

The latest outage affects Marshalltown, parts of the Johannesburg CBD, Wemmer and Selby, as well as sections of Albert, Eloff, Commissioner and Anderson streets.

The affected areas have already experienced prolonged electricity disruptions in recent weeks. Repeated damage to the substation has complicated restoration work, leaving some residents and businesses struggling to resume normal operations.

City Power said technicians would only enter the underground tunnel after the necessary safety clearance had been granted. The team must first determine the extent of the damage before deciding what repairs are required.

At the time of reporting, the cause of the latest fire had not been established, and no confirmed restoration time had been announced.

A Troubled Substation With a History of Fires

The Central Substation is an important part of the electricity network serving Johannesburg’s inner city and surrounding neighbourhoods.

Earlier fires in September and October damaged equipment and cables, repeatedly delaying restoration. City Power has previously raised concerns about suspected cable theft, vandalism and unauthorised access to electricity infrastructure in the area.

The utility has also warned that damage to underground cables and equipment can make repairs more complicated because technicians must inspect the affected infrastructure, replace damaged components and carry out safety tests before reconnecting customers.

Although earlier incidents were linked to suspected criminal activity, authorities have not yet confirmed what caused Tuesday’s latest fire. Its cause must be established through an investigation rather than assumed from previous incidents.


Businesses Continue to Bear the Cost

Repeated power outages can be particularly damaging for small businesses that rely on refrigeration, lighting, electronic payment systems and machinery.

Restaurants and supermarkets risk losing perishable stock, while accommodation providers and manufacturers may be unable to serve customers or continue production. Businesses that use generators face additional fuel and maintenance expenses.

In an earlier report published by TimesLIVE, Johannesburg business owners described losing customers and struggling to pay operating expenses during the extended outage linked to previous substation damage.

The latest incident threatens to prolong those difficulties, especially for businesses that have already spent money trying to remain operational during earlier disruptions.

Residents also face the inconvenience of interrupted household activities, while people who depend on electricity for work or essential services may need to make alternative arrangements.

Why Repairs May Take Time

Restoring electricity after a major substation fire involves more than switching the power back on. Emergency services must first establish that the site is safe, after which technicians can inspect the damaged equipment and determine which parts of the network can be repaired.

The affected systems then need to undergo the required checks and testing before they can be safely returned to service.

City Power has previously used alternative supply routes and staged restoration to reconnect some customers while repairs continued. Whether those options are available following the latest fire will depend on the condition of the equipment and the wider network.

Residents Await a Restoration Update

The immediate priority is to secure the site, assess the damage and establish what work is necessary to restore the affected areas.

Residents and business owners should follow official City Power updates for confirmed information about repair progress and electricity restoration. Members of the public should also stay away from the substation and restricted work areas while emergency and technical teams carry out their duties.

With repeated incidents continuing to disrupt the inner city, the latest fire has renewed concerns about the security and reliability of Johannesburg’s electricity infrastructure.

Author: SA BUZZ NEWS TEAM

Sources

  1. TimesLIVE — Fourth fire at Joburg Central Substation triggers fresh power outage

  2. The Citizen — Fire damage and vandalism add to Joburg Central Substation woes

  3. Eyewitness News — City Power concerned about repeated electricity infrastructure vandalism and theft